Construction Process

Property Site Plan

1st step – Blueprints/Permits: Before we begin with the project, we have to create a site plan. On the site plan we draw the whole property showing the location of the pool, pool equipment, property lines, walls, gates, house, garage, patios, and anything that is require by the city. Once we have the site plan and the engineering structural plans of the pool, we can submit them to the building and safety department to obtain the building permits.

 

 

Pool grading, layout, and excavation

2nd step – Layout/Excavation: The area where the pool will be located is graded to the correct elevation. Once the pool layout is establish, we form the pool to start the excavation.

 

 

Structural steel (rebar)

3rd step – Reinforcing steel (Rebar): After excavating the pool we begin to install the rebar. The rebar is installed throughout the entire pool according to the engineering plans.

 

 

Pool and spa plumbing

4th step- Plumbing/Electrical: The plumbing and electrical lines are then installed. For example: the skimmer, jets, return lines, and electrical for pool lights and controls.

 

 

Swimming pool gunite applicaiton

5th step – Gunite: After the plumbing and electrical, the next step is to apply the gunite which creates the shell of the pool. The gunite is the process of applying concrete to the walls of the pool.

 

 

Masonry

6th step – Masonry: This is the step where everthing comes together. We do the coping, tile, waterfall, or anything that was agreed in the contract.

 

 

Pool equipment

7th step – Pool equipment/plaster: The last step is to install the pool equipment such as the filter, circulation pump, jet pump, heater, and electrical control system. Once the pool equipment is installed, we plaster the pool and begin to fill it with water.